Circuit Breaker Sizing Calculation: A Step-by-Step Guide

Circuit breaker sizing calculation for medium- and high-voltage circuit breakers basically involves two symmetrical current calculations, one for the first cycle duty and another for the interrupting duty. This guide presents a step-by-step approach. A sample calculation is provided in each step to reinforce learning.

Don’t want to go through the manual calculation process?

Use our ‘Circuit Breaker Sizing Calculator‘ instead.

Circuit Breaker Sizing Calculation: First Cycle Duty

1. Using the ½ cycle network impedances, construct the impedance diagram of the system. Refer to the impedance table presented here.

Figure 1. 1/2 Cycle Impedance Diagram

*Note: The values presented in this example are overly simplified. Highlight is given to the calculation process instead.

2. Calculate the Thevenin’s equivalent impedance.

Figure 2. Thevenin’n Equivalent Circuit

Alternatively, you may use the equivalent impedance calculated using the separate X and R networks. This approach is generally conservative.

3. Calculate the symmetrical RMS current using the following formula.

where Vpre-fault is the line-to-line fault point voltage and is equal to the operating voltage under actual service conditions.

*Note: The solution for the symmetrical RMS current is calculated from the actual voltage and ohmic value of the impedances. For more systems with two (2) or more voltage levels, use per unit approach.

4. Calculate the fault point X/R ratio using the separate X and R reduction process.

Figure 3. Separate X and R Networks

5. Calculate the first cycle asymmetrical peak current multiplying factor using the following formula.

6. Calculate the first cycle asymmetrical peak current by applying MFpeak to the previously calculated symmetrical RMS current.

7. Calculate the first cycle asymmetrical RMS current multiplying factor using the following formula.

8. Calculate the first cycle asymmetrical rms current by applying MFrms to the previously calculated symmetrical RMS current.

Circuit Breaker Sizing Calculation: Interrupting Duty

1. Calculate the interrupting duty multiplying factor using the following formula.

2. Calculate the No AC Decay (NACD) using the ratio of the remote generators (if available) fault current contribution to the total available fault.

In our example, the remote contribution to the fault comes from the utility source. Using common circuit analysis technique such as current division and/or superposition theorem, the remote contribution can be easily calculated to be

From this, we can calculate the NACD ratio.

3. Calculate the remote multiplying factor using the X/R ratio at the fault point and a CPT of 2 cycles.

Adjust MF for symmetrically rated circuit breaker.

Verify circuit breaker rating structure. For totally rated circuit breakers use S = 1. For symmetrically rated circuit breakers use the S-factor indicated on the nameplate. If not available, use the S-factor provided in C37.010-1979. You can access this table here.

In our example, we assume a symmetrically rated circuit breaker. With a CPT of 2 cycles, the S factor is equal to 1.2.

4. The local multiplying factor can be derived from the local curves provided in IEEE Std C37.5 for totally rated circuit breakers and IEEE Std C37.010 for symmetrically rated circuit breakers.

In our example, the fault point X/R ratio was calculated to be 13.29. Selecting the multiplying factor for a CB interrupting time of 3 cycles (CPT = 2cycles), we get

Again, adjust MF for symmetrically rated circuit breaker.

5. Calculate the AMF.

6. Calculate the circuit breaker interrupting duty using the following formula.

Since reactances for ½ cycle and 1.5 – 4 cycle network are the same for both utility and generator,

*Note: In calculating for the interrupting RMS symmetrical current, use reactances on the 1.5 – 4 cycle network.

That’s it for circuit breaker sizing calculation. Share your insights by leaving a comment below.

References

IEEE Std 551-2006 [The Violet Book]: Recommended Practice for Calculating AC Short-Circuit Currents in Industrial and Commercial Power Systems. (2006). S.I.: IEEE.

IEEE Std C37.5-1979: ANSI Guide for Calculation of Fault Currents for Application of AC High-Voltage Circuit Breakers Rated on a Total Current Basis. (1979). S.I.: IEEE.

IEEE Std C37.010-2016: IEEE Application Guide for AC High-Voltage Circuit Breakers > 1000 Vac Rated on a Symmetrical Current Basis. (2016). S.I.: IEEE.

IEEE Std C37.04-2018: IEEE Standard for Ratings and Requirements for AC High-Voltage Circuit Breakers with Rated Maximum Voltage Above 1000 V. (2018). S.I.: IEEE.

ETAP Enterprise Solution for Electrical Power Systems Online Help

You may want read these articles:

Short Circuit Study: An Introduction to Circuit Breaker Sizing

Circuit Breaker Interrupting Rating Calculations 

kAIC Rating of Circuit Breakers: Calculation in Low Voltage System

pacbasics

View Comments

  • Great article!

    There are two points I wish to know though.

    What is the use of the first duty cycle rating and is the breaker intended to interrupt during the first cycle? And is it really a symmetrical current calculation?

    Would appreciate if you add this in the article.

    Thanks!

    • Hi there!

      Thanks for commenting.

      > First cycle duty is used to verify if the circuit breaker can withstand the short-circuit current magnitude at the instant of the fault. Low voltage circuit breakers interrupt during this time but for medium- and high-voltage circuit breakers, the interruption happens after at least 1.5 cycles from initiation of the fault. You can refer to this link for more info. https://pacbasics.org/short-circuit-study-an-introduction-to-circuit-breaker-sizing/

      > Symmetrical current calculation is done because it's simpler. You can use V/Z approach to that. To account for the dc quantity which makes the fault asymmetrical, we apply multiplying factors. Simple, right?

Share
Published by
pacbasics

Recent Posts

2 Key Metrics in Overcurrent Protection: Why Time-Current Curves and Coordination Time Intervals Matter More Than You Think

TCC and CTI are the two most common acronyms in overcurrent protection coordination. Understanding Time-Current…

4 weeks ago

Transformer Tertiary Winding Basic Application

Tertiary winding in transformers have been widely used in the transmission and distribution of electricity…

5 years ago

How Do Reclosers Work? Settings and Operation

Photo Credit: NOJA Power Reclosers, otherwise known as autoreclosers (derived from "automatic reclosing" capability) or…

5 years ago

Impedance-Based Fault Location | A Step-by-Step Guide

Impedance-based fault location is widely used throughout the power transmission and distribution industry. In fact,…

5 years ago

Distance Relaying Fundamentals | What is Apparent Impedance?

In our introductory article on distance relaying, we presented a simple apparent impedance calculation for…

5 years ago

ETAP Star Coordination on Focus | Detailed Example

The main objective of any protection system is to interrupt short-circuits as fast as possible.…

6 years ago